Bike Rider

Local Trail News

Fall color on the trail

August 23, 2010

Morningside Cable Bridge over S. Peachtree Creek

PATH and the City of Atlanta are building a cable bridge connection over South Peachtree Creek in Wildwood Forest.

Construction began in July. Main support posts have been erected. Cables and decking will be installed beginning the week of Sep 7th




August 16, 2010

South Peachtree Creek Trail, Phase 2

Work will begin to extend the South Peachtree Creek Trail over the CSX track and to the Mason Mill Tennis Center in early September.

Watch this spot for weekly updates.




August 9, 2010

Chastain Park Trail Phase 7

PATH crews are building the trail connection between the Tennis Center and the Red Lot near the Amphitheatre. Construction began in mid July and will continue through September.

The project will include sealing and restriping the Red Lot and a trail connection to the parking area from the balance of the trail system.



Visit Arabia Mountain Trail
Riders and the Atlanta skyline
Web design and development by MediumCool.